| January 1999 |
|
Award of the design contract to the architecture and engineering firm "Werkgruppe 1" of Bleibach. |
| March 1999 |
|
Request for permits and authorizations submitted to the authorities. |
| April 27th 1999 |
|
Issue of the permits and authorization for the factory including its integrated hydropower plant on the river Elz. |
| May 1st 1999 |
|
Groundbreaking ceremony and planting of a memorial tree. |
| Mid June 1999 |
|
Construction of the factory starts. |
| December 1999 |
|
Flooding and tropical storm "Lothar" seriously threaten the construction. Fortunately damage was only slight. |
| December 29th 1999 |
|
Trial run of the WKV Francis turbines. |
| December 31st 1999 |
|
The last workmen leave the construction site at 16:00. The powerplant is set up and decorated for the year 2000 celebrations. After an extensive celebration program the many guests toast the new millennium - in a zone free of nuclear power produced electricity! |
| From January to April 2000 |
|
Installation and completion of the remainder of the facilities. |
| End of April 2000 |
|
Landscaping and outside installation are completed. |
| May 1st 2000 |
|
Many thousands of visitors attend our "open-doors"-event in our state-of-the-art factory. The guest speaker, TV-journalist Dr. Franz Alt, addresses the visitors on the subject of "A change of course for our energy supply...". |
May 17th 2000
 |
|
The company management and administrative staff move into our state-of-the-art factory. |